T-39 Project Photos

Print
Press Enter to show all options, press Tab go to next option

December 3, 2019 Construction Photos

01 Installing Fencing on top of Wal02 Curb Installation
         
  Installing Fencing on top of Wall                                                  Curb Installation               

03 Wall Under Drain 04 Irrigation Installation
Wall Under Drain                                                          Irrigation Installation

05 Installation of Wall Gutter 06 Irrigation Installation
Installation of Wall Gutter                                                Irrigation Installation

07. Asphault Paving 08 Asphault Paying 2
Asphalt Paving                                                                    Asphalt Paving 2

09 Planter Strip 010 Landscaping in Planter Strip 1
                       Planter Strip                                                         Landscaping in Planter Strip        
011 Landscaping in Planter Strip 2
Landscaping in Planter Strip 2


October 4, 2019 Construction Photos

025 2019 0918 - Sidewalk & Planter Strip026 2019 0926 - Wall Under Drain
Sidewalk and Planter Strip                                                  Wall Under Drain       

027 2019 0927 -Wall Prep Prior to Painting028 2019 0930 - Traffic Signal Conduit
Wall Prep Prior to Painting                                         Traffic Signal Conduit

029 2019 1002 - Pouring of Wall Panal
Pouring Wall Panel


  August 30, 2019 Construction Photos

2019 0823 - Wall Rebar Sheet - 8302019 0826 - Roadway - 083019
              Panel Pours                                                                      ADA Ramp Preparation          

2019 0827 - Roadway - 083019 2019 0828 - Wall Rebar Sheet
                                        Future Bus Pad                                                                Finished Soldier Pile Wall                                           

 2019 0829 - Roadway  2019 0829 2 - Roadway
                      Sidewalk                                                                          ADA Ramp Preparation        


 August 5, 2019 Construction Photos

104, Wall Rebar sheet 1-19.07.26-9.59PM-104, Wall Rebar sheet 1 Photo markup_1 104, Wall Rebar sheet 1-19.07.29-6.29PM-104, Wall Rebar sheet 1 Photo markup
Wall Panels                                                                           Wall Panels

104, Wall Rebar sheet 1-19.08.01-11.41PM-104, Wall Rebar sheet 1 Photo markup 104, Wall Rebar sheet 1-19.08.02-4.37PM-104, Wall Rebar sheet 1 Photo markup
Wall Form                                                              Cleaning Wall Form

22, RD05 Roadway-19.08.01-5.27PM-22, RD05 Roadway Photo markup_1 22, RD05 Roadway-19.08.01-8.30PM-22, RD05 Roadway Photo markup
Curb Placement                                                                  Curb Placement


July 19, 2019 - Construction Photos

44, WL02-19.07.02-5.38PM-44, WL02 Photo markup_1 44, WL02-19.07.03-6.34PM-44, WL02 Photo markup
Welding Nelson Studs                                          Placing Wood Lagging

22, RD05 Roadway-19.08.01-8.55PM-22, RD05 Roadway Photo markup
Curb Placement

44, WL02-19.07.17-9.03PM-44, WL02 Photo markup 44, WL02-19.07.17-9.03PM-44, WL02 Photo markup_1
Installing Rebar

44, WL02-19.07.17-9.07PM-44, WL02 Photo markup 46, WL04-19.06.26-3.00PM-46, WL04 Photo markup
Wall Preparation                                             Pile Installation


June 24, 2019 - Pile Wall and Wall Lagging Construction

001 Pile Wall Construction002 Pile Wall Construction
Soldier Pile Tools                                            Soldier Pile Hole

003 Pile Wall Construction004 Pile Wall Construction
Auger                                                     Steel Piles

005 Wall Lagging006 Wall Lagging
Soldier Pile Lagging

007 Wall Lagging008 Wall Lagging
Soldier Pile Lagging                                        Tree Inventory            

009 Wall Lagging010 Pile Wall Construction
Soldier Pile Wall Construction

011 Pile Wall Construction012 Pile Wall Construction
Concrete Placement in Shaft                                       Augar Shaft       

100 Storm Water Pipe Construction
Storm Drain Installation


 May 24, 2019 Construction Photos

31, DR04-19.05.17-5.33PM-31, DR04 Photo markup_143, WL01-19.05.20-6.49PM-43, WL01 Photo markup

                                    Install Storm Water Catch Basin                                   Soldier Pile Drilling

 

43, WL01-19.05.20-7.02PM-43, WL01 Photo markup  

Soldier Pile Drilling

 

  43, WL01-19.05.23-3.05PM-43, WL01 Photo markup

                                 Soldier Pile Concrete                                               Soldier Pile Drilling

 


May 5, 2019 Construction Photos

31, DR04-19.05.06-3.50PM-31, DR04 Photo markup    34, DR07-19.05.09-7.45PM-34, DR07 Photo markup
Storm Drain Infiltration  Chamber


April 29, 2019 - Site Prep

11, SP02 site prep-19.04.29-6.10PM-11, SP02 site prep Photo markup12, SP03 Site Prep-19.04.29-8.00PM-12, SP03 Site Prep Photo markup
Tree Falling


April 25, 2019

92, CS02-19.04.25-2.40PM-92, CS02 Photo markup
Traffic Control


April 22, 2019 

1, CV01-19.04.22-2.48PM-1, CV01 Photo markup
Pavement Marking