T-39 Project Updates

Print
Press Enter to show all options, press Tab go to next option

T-39 Project Update Flyer Links:

April 18, 2019


May 24, 2019 Update:

  • Stormwater infiltration system has been installed and covered.
  • The soldier pile wall construction has begun along the north portion of the project.  DMI a subcontractor to Johansen is onsite and have completed approximately 17 of the 122 drilled piles.
  • Soon work will start on placing wood lagging between the piles.
  • No changes to the current traffic control is anticipated for a while.


May 10, 2019 Update:

  • Johansen Construction Co. has installed concrete barriers along the work zone, striping has been completed to allow 2 lanes of traffic southbound and 1 lane northbound
  • Clearing activities are complete and the bench for the wall has been graded
  • Steel for the wall is at the fabricator and will arrive the week of May 20th
  • Stormwater construction is underway with the installation of an infiltration gallery
  • Night work will be occurring on Monday, May 13th and Tuesday, May 14th, 9 p.m. until 4 a.m., on SR 169 between Witte RD and SE 225th.  The road will be reduced to 1 lane of alternating traffic.  Centrylink will be abandoning a telephone line in an underground vault in the road for the T-39 project.