Project T37 

  • Project Cost: approx. $570,000
  • Funded by City & Federal Grant (WSDOT - FHWA)
  • Project Priority: High
  • Project Schedule: Signal operational as of 5/20/14.
  • Construction began August 2013. 
  • Substantial completion as of July 2014.  Physically Complete.